Case Study Contributors
Location
Big Manistee Watershed, Huron-Manistee National Forest, Michigan, USA. MAP
Project Type
Pre-Project Conditions
Pre-Project Barrier
Watershed Characteristics
Ecological Value
Project Characteristics
Challenges
Project Contributors
Project Funding
Completion Date
October 2005
Total Project Cost
| Materials | $ | 39,000 |
| Construction | $ | 33,000 |
| Planning/Permitting | $ | 1,000 |
| Total | $ | 73,000 |
Project Summary
This was a cooperative project between the Little River Band of Ottawa Indians and the U.S. Forest Service. Design work was performed by the arch manufacturer, with the Forest Service providing site survey, geotechnical study and design review.
The crossing had twin culverts that created a jump and velocity barrier, blocking upstream movement of native resident fish and potadromous salmonids. Replacing the undersized twin culverts on Sickle Creek with a precast concrete arch allowed for fish passage, lessened the risk of crossing failure, and improved road drainage to reduce fine sediment delivery to the steam.
The streambed substrate is predominately sand with some gravel and the undersized culverts created a deposit of aggraded sands upstream of the crossing. No grade control was planned for the site but an in-stream sediment trap was constructed downstream of the crossing to catch some of the upstream deposition as it mobilized. The sediment trap was a pool dug 8 ft long and 6 ft deep (2.4 m x 1.8 m) that spanned the channel. It filled up within eight hours, preventing the aggraded sediment from being transported further downstream
The top of the arch is designed to have 3 ft (0.9 m) of freeboard during the 100-year return period flow. Concrete footings were poured in place using sheet pile to form one side and left in place to protect the footings from scour.
Challenges
Because the site was a main access road to a high-use area of the Manistee River, construction had to be completed in one week and during the wet season. This led to a short curing time of three days for the concrete footings, raising concerns about its ability to accommodate the design loading. However no problems have arisen.
A crane was used to lift and place the precast sections onto the footings. Because of the room required to swing the crane, some trees were removed to provide adequate clearance.
Post-project Challenges and Lessons Learned
The Tribe and Grand Valley State University are currently collaborating on post construction monitoring of fish, macroinvertebrates, and sediment. Stream profiles and transects have revealed only minor upstream headcutting and channel adjustment.
Fish sampling as part of the ongoing study indicated increases in salmon parr following replacement of the culvert in the spring of 2006. Additionally, native sculpin, and invasive sea lamprey have increased upstream of the crossing following replacement.
| Spring 2004 | Fall 2004 | Spring 2005 | Fall 2005 | Spring 2006 | Fall 2006 | |
| Chinook Parr | 17 | 6 | 2 | 6 | 107 | 31 |
| Coho Parr | 35 | 8 | 12 | 0 | 23 | 0 |
Initially, there was some resistance to installing a bottomless arch culvert since it was the first use of this structure type on the Manistee Forest. The structure has been in place for a year and a half, and is easily passing the high spring flows. Many people have commented that the appearance of the new crossing is more appealing than the previous culverts.
Published 01/21/07